Panera Bread
Niles, OH
Project Details:
MetalWrap Series 200 was installed over 6,500 square feet of this free-standing Panera Bread store in only 4 days. The brick facade was installed over MetalWrap Series in only 6 days. The project was completed in Fall 2010.
Architect: Phillips Sekanick Architects, Inc.
General Contractor/Installer: Murphy Contracting
Masonry: Lencyk Masonry
Why MetalWrap Series?
The architect stressed that this project needed to be completed on a very strict time schedule. The project began on September 7, 2010 with a company who had never installed MetalWrap Series 200 before. By September 11, 6,500 square feet of MetalWrap Series 200 high performance wall was completed. By September 21, the back-up wall was in place with brick anchors and the walls were completely bricked in. The architect also expressed that he selected MetalWrap Series for its unique performance features.
Site Experience:
Those working onsite were pleased with the ease of installation and the ability to work quickly on a very tight project schedule. The general contractor mentioned that the MetalWrap Series system allowed other trades to work inside of the building while they finished outside trades such as the masonry.